Reedbed Project Example
Clean-Out & Reed Transplanting of Multi-bed System
- Work undertaken on beds 1, 5, 7 & 8 
- Clean-out of reedbed to lower very high water levels across multi-bed system 
- Works required: - - Construction of access road around the mountain and Forestry Commission area - - Installation of bypass pipework for watercourse diversions from the adits 
- Sludge/reed removal from reed beds 
- Transplanting of reeds 
 
                         
            
              
            
            
          
               
            
              
            
            
          
              